PacifiCorp has launched Energy Gateway -- an ambitious transmission expansion program that will add more than 1,700 miles of new transmission lines across the West. The plan was announced in May 2007 , and siting and permitting processes now are underway for many segments of the planned expansion. The more than $4 billion project is planned for completion in 2014. Read more about the overall project in the fact sheet , or for answers to commonly asked questions, view the Frequently Asked Questions sheet .

Segments of the expansion are listed below with planned in-service dates. Each are linked to project documents - which we will update as new information develops. The map shows the segment additions to the transmission system when the expansion is completed.

  Segment name   Planned in-service date
  Segment A -Walla Walla to McNary  2010
 Segment B -Populus to Terminal  2010
 Segment C - Mona to Oquirrh  2012
 Segment D - Windstar to Aeolus to Bridger  2012
 Segment E - Jim Bridger to Populus to Hemingway  2012
 Segment F - Aeolus to Mona  2013
 Segment G - Sigurd to Red Butte to Crystal  2012
 Segment H - Hemingway to Captain Jack  2014







(updated June 1, 2008)